How Long Does a Kitchen Remodel Take? Our Week-by-Week Timeline in Plantation, FL

So, how long does a kitchen remodel take? Based on our 30 years remodeling homes in Plantation and across South Florida, the construction itself takes about 4 to 8 weeks from the day of demolition to the day of final cleaning, depending on the scope. A same-layout kitchen can be done in about 4 weeks; a complete redesign with plumbing and electrical relocation runs 6 to 8 weeks. Add design, selections, ordering and permits before demolition, and a typical project runs about 2 to 4 months from your first consultation to the final walkthrough.

“Some contractors promise a kitchen remodel in two weeks or less. That’s not doable if you’re expecting a quality finished product. Based on our 30 years’ experience, most kitchen remodels take between four and six weeks from demolition to the final cleaning, and a complete redesign can take up to eight.”— Dasiel Duran, Owner, Fresh Remodel

The part that surprises most homeowners is that the longest wait often happens before anyone touches the kitchen. Countertop fabrication alone takes 7 to 10 business days after cabinets are in place, because it is a custom-made product that cannot even be templated until the base cabinets are installed. That is why honest timelines matter more than fast promises.

Kitchen remodel timeline in short:

  • Design and planning: about 2–4 weeks (consultation, budget analysis, product selections, 3D views and contract).
  • Product ordering and inspection: about 2 additional weeks after contract signing.
  • Construction (same layout): about 4 weeks from demolition to cleaning.
  • Construction (complete redesign): about 6–8 weeks when relocating plumbing, electrical or building new walls.
  • Your start and finish dates are written into our contract.

Our 8-Step Kitchen Remodel Process (and How Long Each One Takes)

At Fresh Remodel, we understood that to deliver a timeline with a high-quality finished product, we had to create a meticulous step-by-step process — from designing to cleaning — so our customers receive a better result and a happy finished product.

  1. 1Discovery call: Our first step is a short conversation with our designer to understand what you want to do, and for you to understand how our process works. You can explain your project, we explain our approach, and together we decide if it is a good fit — based on scope, timing, knowledge and pricing.
  2. 2In-home consultation (free): Our designer visits your home to understand the style, ideas, concept and space. We take exact measurements of the work area and ask questions about your ideas and expectations. This entire consultation is completely free.
  3. 3Project analysis presentation: Our designer prepares a full presentation explaining how the remodeling process will go. You receive a close estimate of the final cost, a step-by-step timeline of what comes next, and a chance to visit our showroom — so you can make a smarter decision about moving forward.
  4. 4Design phase and contract (weeks 2–4): After you decide to move forward, our designer presents the options, their pros and the selections that match the style you want, along with a detailed breakdown of where every dollar goes in products and labor. You see 3D views of exactly how your finished kitchen will look. This is also when we sign the contract. From the first in-home consultation to contract signing, the average is about 4 weeks — though this can vary if you want to explore additional options.
  5. 5Product ordering and inspection (~2 weeks after contract): We order every single product that will be used in your project — on average, three to six pages of items. We receive and inspect every product before the project starts, and we make sure each one matches the design you approved. This is something unique to our company: by having everything delivered, verified and ready, we avoid the mid-project delays that happen when other companies realize a part has not arrived yet.
  6. 6Project kickoff and construction (4–8 weeks): Our foreman and project manager prepare the work area, keep it clean and secure, protect all pathways and adjacent spaces, and start demolition. From there, we move step by step through electrical, plumbing, wall work, flooring, cabinets, countertops and painting — all the way to completion.
  7. 7Final walkthrough: We do not consider the project complete until our customers are fully happy. We do a deep walkthrough of every single detail, noting anything that needs to be corrected, fixed or adjusted — down to the last minimum detail.
  8. 8Post-construction cleaning: As a complimentary service, we send a specialized post-construction cleaning crew to deep-clean not only the kitchen area, but all adjacent areas — making sure no trace of dust or construction materials is visible anywhere.

Kitchen Remodel Timeline: Same Layout vs. Complete Redesign

How long does a kitchen remodel take once construction starts? It depends on the scope. Here is how both scenarios break down:

Same Layout Kitchen: ~4 Weeks

Keeping the same layout means no relocating of electrical, no major wall removal, and no new wall installations. The work includes:

  • Kitchen removal and prep
  • Electrical and plumbing adjustments
  • Floor repair (gaps found after cabinet removal)
  • Cabinet installation
  • Countertop template, fabrication and install (7–10 business days)
  • Backsplash, fixtures and finishing

Could it be done in 3 weeks? Maybe. But we prefer to say 4 weeks upfront because in construction, surprises happen — the backsplash, the countertops, something unexpected — and we want to give you honest numbers from day one.

Complete Redesign: 6–8 Weeks

A full redesign means rethinking the use of the space. This typically involves:

  • Relocating water lines, piping and drains
  • New 220V circuits from the panel for additional outlets
  • Wall demolition or new wall construction
  • All the work from a same-layout remodel, plus the extra rough-in

The additional structural and utility work adds roughly 2 more weeks to the process, bringing the total to 6–8 weeks from demolition to completion.

Week-by-Week Construction Breakdown

This is how a typical 6-week kitchen remodel in a Plantation home breaks down once demolition starts:

Week What happens What you will notice
Week 1 Protection, demolition, debris removal; plumbing and electrical rough-in starts Noise and dust control; the kitchen is out of service
Week 2 Rough-in finished; inspections; drywall repairs; flooring prep Inspector visits; walls closed up
Week 3 Flooring (when included) and cabinet installation The kitchen starts to look like a kitchen again
Week 4 Countertop template; fabrication begins at the shop A quieter week while the stone is cut
Week 5 Countertop installation; sink, faucet and cooktop connections; backsplash Water is back at the sink
Week 6 Appliances, lighting, hardware, paint touch-ups, final inspection and walkthrough Your new kitchen is ready

A typical sequence for a full kitchen with semi-custom cabinets and quartz. Same-layout kitchens can finish in about 4 weeks; moving walls, plumbing or adding new circuits adds time. Replacing the floor too? It fits into week 3; see our flooring installation services.

“After the cabinets go in, you have between seven to ten business days for the fabrication of the countertop installation — it’s a custom-made product that we cannot even template unless the base cabinets are in place. Just right there, you have almost two weeks of the entire process. That’s why we give you real numbers upfront.”— Dasiel Duran, Owner, Fresh Remodel

Finished kitchen remodel with white and wood-look cabinets; how long does a kitchen remodel take depends on scope
A standard-layout kitchen moves fastest.
Modern kitchen with dark wood cabinets and glass mosaic backsplash remodeled by Fresh Remodel
Custom details and backsplash add finishing days.

Get a Kitchen Schedule in Writing

Our contracts include guaranteed start and finish dates. Call us for a free in-home consultation.

Call (954) 859-5189

What Makes a Kitchen Remodel Take Longer

When clients ask how long does a kitchen remodel take, these are the factors that can stretch the timeline:

City Permits and Inspections

The single biggest factor. If the city is involved with permitting, drawings and inspections, it adds significant time. Turning construction drawings into city-approved plans — with all the information required by different departments — can take 1 to 2 additional months before you can even start demolition.

Scope Changes and Redesign

  • Relocating plumbing, drains or electrical adds 2+ weeks
  • Wall demolition or new wall construction
  • Adding new 220V circuits from the panel
  • Changing selections after the design phase (the designer goes back to the drawing board)

Unforeseen Conditions

  • Hidden plumbing or electrical issues behind old cabinets
  • Floor gaps or damage found after cabinet removal
  • Backsplash or countertop complications
  • Back-ordered appliances or fixtures

Still choosing materials? Compare countertops in our guide to quartz vs granite vs marble for Plantation kitchens, and kitchen floors in our laminate vs vinyl comparison. Selections made before demolition keep the schedule on track.

Permits and Inspections in Plantation and Broward

Any kitchen remodel that touches plumbing, electrical or gas needs a permit and inspections. When the city is part of the process, it becomes the most significant factor in timeline delays. The drawings must meet requirements from multiple departments within your city’s building department. After submissions, approvals and revisions, permit processing alone can add 1 to 2 months before construction begins.

We file the permits and schedule inspections as part of the project, so the timing is already in your schedule from day one. Permits also affect the budget: in our experience, they can add 10–15% to the total cost of a kitchen remodel, all included. Learn what needs a permit, what may be exempt under Florida’s new $7,500 rule, and what it really costs in our guide to remodeling permits in Plantation and Broward County.

Have a deadline, like a holiday or a family visit? Tell us early and we will plan the schedule backward from that date. Call (954) 859-5189 for a free in-home visit.

Living Without a Kitchen During the Remodel

A few weeks without a kitchen is easier with a plan:

    • Set up a temporary kitchen in the laundry room, dining room or garage: refrigerator, microwave, coffee maker and an electric kettle.
    • Use the outdoor grill. One advantage of South Florida: you can cook outside almost all year. (If you have been thinking about a full outdoor kitchen, this is when most families realize how much they would use it.)
    • Stock paper plates and one-pot meals to avoid washing dishes in a bathroom sink.
    • Protect the rest of the house. Our crew secures and protects all pathways and areas that lead to the project site. We contain dust and keep every adjacent area clean throughout the process.
    • Plan around holidays. If you want the kitchen ready for Thanksgiving or a family visit, start planning 3–4 months ahead.

Why Our Process Keeps Your Timeline on Track

The difference between a kitchen remodel that finishes on time and one that drags on comes down to preparation. Our 8-step process was designed specifically to eliminate the delays that happen at other companies.

How we prevent delays:

  • Everything is ordered before demolition. After contract signing, we order every single item — averaging three to six pages of products — and receive and inspect them before the project starts.
  • No mid-project surprises. Because we verify that every product is the right one and arrives on time, we do not need to stop and wait like companies that discover a part is missing halfway through.
  • Countertop timing is built into the schedule. We know the 7–10 business day fabrication window for countertops, so it is already accounted for — not a surprise.
  • The final walkthrough is thorough. We do not consider the project complete until every detail is corrected, fixed and adjusted to the customer’s satisfaction.

How Long Does a Kitchen Remodel Take: FAQ

How long does a small kitchen remodel take?

The size of the kitchen is actually not a major factor in how long the project takes. A larger kitchen may add a few hours for more cabinets, a larger countertop area, or a bigger backsplash. Extra lighting — like under-cabinet lights — may add one or two days to the process. But overall, a small kitchen that keeps the same layout can be completed in about 4 weeks of construction, once cabinets and materials are ready.

How long does the design and planning phase take?

In our company, the design and planning phase takes about 2 to 4 weeks. The first 1–2 weeks cover the in-home consultation, understanding your ideas, and preparing the budget analysis — all at no cost to you. The next phase involves product selections, detailed proposals for every item and labor cost, construction drawings, plans, and 3D views. From the first in-home consultation to the day you sign the contract, the average is about 4 weeks. After that, add approximately 2 more weeks for ordering, receiving and inspecting every product before we begin.

How long is the full kitchen remodel timeline from start to finish?

Usually about 2 to 4 months total, including design (2–4 weeks), product ordering (2 weeks), and construction (4–8 weeks on site). If city permits are involved, add 1 to 2 months for the approval process before construction begins.

What takes the longest in a kitchen remodel?

Countertop fabrication and city permits. The countertop is a custom-made product that takes 7–10 business days to fabricate after cabinets are installed, because it cannot even be templated without the base cabinets in place. If permits are required, the approval process across multiple city departments can take 1 to 2 months.

Can I live in my house during a kitchen remodel?

Yes, most of our clients do. We protect the rest of the home, secure all pathways and keep the work area separated. Our post-construction cleaning crew ensures no dust or construction materials remain in any area of the home.

Do you guarantee the finish date?

Yes. Our contracts include guaranteed start and finish dates. Our ordering and inspection process is specifically designed to prevent mid-project delays — we verify that every product is correct and on site before the first day of demolition.

Plan Your Kitchen Timeline With Us

Showroom: 10089 Cleary Blvd, Plantation · Mon–Fri 10 AM–6 PM · Sat 10 AM–3 PM

Call (954) 859-5189Get Directions

Budgeting too? Start with our 10×10 kitchen remodel cost guide or our kitchen remodeling services.

Planning More Than the Kitchen?

A kitchen remodel is often the moment to update what surrounds it. When one licensed General Contractor handles everything, you get one design, one schedule and one contract instead of coordinating several companies, and we follow the same 8-step process on every project. These are the projects that pair most naturally with a new kitchen:

Light wood-look floor continuing through a hallway, installed by Fresh Remodel

Flooring that continues into the living areaThe kitchen floor rarely stops at the kitchen. Replacing it during the remodel avoids patches where the old cabinets sat.Flooring installation →

Modern bathroom with warm oak vanity remodeled by Fresh Remodel

Bathrooms that match the new kitchenThe same designer can coordinate cabinets, countertops and tile so the whole home feels consistent.Bathroom remodeling →

Outdoor kitchen island with stainless appliances and ceiling fans in Plantation

An outdoor kitchen for year-round cookingIn South Florida, much of the cooking and entertaining happens outside. Extend the new kitchen to the patio.Outdoor kitchens →

Two-story home addition and construction project by Fresh Remodel in South Florida

More room than the walls allowIf the island or dining area you want does not fit, a home addition can create the space.Home additions →

We also build pergolas, install impact windows and doors, replace roofs and build custom homes across Broward and North Miami-Dade.

Kitchen Remodeling in Plantation and Surrounding Communities: Headquartered in Plantation since 1996, Fresh Remodel plans and builds kitchen remodels on schedule for homeowners in Plantation, Sunrise, Davie, Fort Lauderdale, Lauderhill, Weston, Tamarac, Lauderdale Lakes, Cooper City and Pembroke Pines, and throughout Broward County (Coral Springs, Parkland, Coconut Creek, Margate, Pompano Beach, Deerfield Beach, Hollywood, Hallandale Beach, Miramar, Southwest Ranches, Wilton Manors and more) and North Miami-Dade (Aventura, Sunny Isles Beach, Golden Beach, Bal Harbour, Bay Harbor Islands, Surfside, North Miami Beach, Miami Gardens, Miami Shores, North Bay Village and Miami Lakes). Fully licensed and insured Florida Certified General Contractor, State License #CGC-1506284.